Planning Export Orders Around the Chinese New Year Gap

Planning Export Orders Around the Chinese New Year Gap

Every year, buyers who plan well get their containers before the gap and buyers who plan late spend February explaining a delay. The difference is rarely the length of the holiday. It is understanding how far the disruption reaches in both directions.

What actually happens, in sequence

The holiday itself is a fixed block, but the effects begin earlier and end later:

  • Four to six weeks before. Order intake spikes as buyers rush to beat the closure. Lines fill, and lead times quoted in this window are longer than the same product quoted in September.
  • Two weeks before. Migrant workers begin leaving for home. Effective line capacity drops before the official closure, sometimes significantly, and it drops unevenly by shift.
  • The holiday. Production stops. Ports and freight forwarders run reduced schedules.
  • One to three weeks after. Workers return gradually, not all at once. Lines restart under-staffed and ramp up. New workers need retraining, which affects both speed and defect rates.

A buyer planning against "two weeks of closure" is planning against roughly a third of the real disruption.

The dates move, and that matters

Chinese New Year follows the lunar calendar, so the date shifts each year by up to three weeks. A plan built on last year's dates will be wrong. Any scheduling conversation should start with the confirmed date for the year in question and work backwards.

How to schedule defensively

  1. Place orders before the rush. If goods are needed in the first quarter, the order should be confirmed well before the pre-holiday intake spike, not during it.
  2. Confirm the factory's last production date, not the holiday date. Ask when the last batch will actually come off the line, and when the last container can be loaded.
  3. Book freight early. Space tightens in the weeks before the closure as everyone ships at once.
  4. Split deliveries. Where a programme allows it, shipping part of the volume before the gap and part after reduces exposure to a single window.
  5. Plan the ramp-up. Goods ordered for post-holiday delivery should assume a slow first fortnight.

What to ask a factory in the fourth quarter

  • When is the last date you will accept a production order before the closure?
  • What is the last container loading date you can commit to?
  • How does your line capacity in the four weeks before the holiday compare with a normal month?
  • When do you expect to be back at full capacity afterwards?

A factory that answers these precisely has a production plan. One that answers with the holiday dates alone is telling you it plans to the calendar rather than to capacity.

The inventory alternative

Some buyers solve this by holding buffer stock across the gap rather than trying to schedule around it. That trades warehousing cost and shelf-life considerations against scheduling risk, and it only works if the product has adequate shelf life and the volumes are predictable.

For programmes that cannot hold stock, scheduling is the only lever, and it has to be pulled early. Our OEM services page sets out how we sequence orders into the first quarter, and the packaging and shipment confirmation guide covers the documentation that has to be in place before loading.

Turn this note into a real production brief

Tell us the product type, target market, pack format and quantity you have in mind. We will reply with material options, tooling considerations and a sample timeline.

Request a quote WhatsApp
WhatsApp contact WeChat QR code

Nafei WeChat QR code